免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!
This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.
电话Tel: 13002979178 OR 邮箱Email: Lngbbs@qq.com
摘要:淮安经济技术开发区污水处理厂是经开区重要的生态环境基础设施,规划总处理规模16万吨/日。根据经开区经济社会发展分期建设,一期工程处理规模8万吨/日。本次扩建为二期一阶段工程,处理规模为4万吨/日,出水水质执行《城镇污水处理厂污染物排放标准》(GB18918-2002..
淮安经济技术开发区污水处理厂是经开区重要的生态环境基础设施,规划总处理规模16万吨/日。根据经开区经济社会发展分期建设,一期工程处理规模8万吨/日。本次扩建为二期一阶段工程,处理规模为4万吨/日,出水水质执行《城镇污水处理厂污染物排放标准》(GB18918-2002)一级A标准,项目竣工后,淮安公司日处理规模将达到12万吨/日,该项目建成是增强生态环境保护的重大举措,将极大改善水生态环境质量,保证经济和社会可持续发展。
The sewage treatment plant of Huaian Economic and Technological Development Zone is an important ecological and environmental infrastructure in the economic development zone, with a planned total treatment scale of 160,000 tons/day. According to the economic and social development of the economic development zone, the construction of the first phase of the project is 80,000 tons/day. The expansion for the second phase of the project, the treatment scale of 40,000 tons/day, effluent water quality implementation of the "urban sewage treatment plant pollutant discharge standards" (GB18918-2002) A standard, after the completion of the project, Huaian company's daily treatment scale will reach 120,000 tons/day, the completion of the project is a major measure to enhance ecological environmental protection, It will greatly improve the quality of water ecological environment and ensure sustainable economic and social development. Since the start of the project, leaders at all levels have attached great importance to and repeatedly visited the site to guide the work, and put forward specific requirements for the progress of the project and the safe and civilized construction. In view of the very tight construction period of the project, Huaian company through inverted schedule, wall map operations, seize the key lines, construction progress report and other measures to promote the construction of the project. 10 days to complete all temporary construction work, 18 days to complete more than 16,000 meters of all pipe pile construction, 12 days to complete more than 40,000 meters of steel sheet pile construction, 80 days to complete 11 monomerous civil construction, 40 days to complete all equipment installation work, to overcome the summer high temperature rain, winter cold snow and other adverse weather, in strict accordance with the progress plan to achieve the construction goal. |