1. 825MW风机采购!这4家整机商分羹

1. Purchase of 825MW wind turbine! These 4 machine manufacturers share the market share


大唐吉林松原市招商引资30万千瓦风电项目(民生、环保类)风力发电机组及附属设备采购第一中标候选人为金风科技,投标报价为4.404亿元,8.MW≤单机容量≤8.5MW。

The first winning bidder for the 300,000-kilowatt wind power project (for livelihood and environmental protection purposes) in Songyuan City, Jilin Province, during the investment promotion activities of the Tang Dynasty Group, for the purchase of wind turbine generators and related equipment, is Goldwind Technology. The bid price is 440.4 million yuan. The single-unit capacity ranges from 8 MW to 8.5 MW.


大唐云南大松坪75MW风电项目风力发电机组及附属设备(含塔筒)第一中标候选人为中车株洲所,投标报价为1.70325亿元,单机容量6.25MW。

The first winning bidder for the wind turbine and ancillary equipment (including tower) of the 75MW wind power project in Daliang Yunnan Dafengping is Zhongchuan Zhuzhou Research Institute. The bid price is 170.325 million yuan, with a single-unit capacity of 6.25MW.


大唐甘肃民勤5万千瓦风电新建项目风力发电机组及附属设备采购第一中标候选人为远景能源,投标报价为0.89亿元,安装‌8台单机6.25MW风电机组。

The first winning bidder for the wind turbine and ancillary equipment procurement of the 50,000-kilowatt new wind power project in Minqin, Gansu Province of the Tang Dynasty is YUNAN ENERGY. The bid price is 89 million yuan, and 8 single-unit 6.25MW wind turbines will be installed.


中广核新能源甘肃玉门70万千瓦光伏光热风电制氢示范项目40万千瓦陆上风电项目风力发电机组采购第一中标候选人为明阳智能,投标报价为6.42亿元,单机容量5000kW及以上。

The first winning bidder for the 400,000-kilowatt onshore wind power equipment procurement of the 700,000-kilowatt photovoltaic-thermal-wind power hydrogen production demonstration project of China General Nuclear Power Group in Jiumen, Gansu Province is Mingyang Intelligent. The bid price is 642 million yuan, with a single-unit capacity of 5000 kW or above.


2. 中船海装预中标!中煤2026年首批风机集采

2. China Shipbuilding Marine Equipment has been preliminarily selected as the winner! China Coal's first batch of wind turbine procurement in 2026


近日,中国中煤2026年第一批风电项目风力发电机组集中采购开标,中船海装为第一中标候选人,投标报价82035.18万元,项目为中煤西北公司336.6MW火电灵改、90MW厂用电新能源项目风电设备(含塔筒及锚栓)采购。  

Recently, the bidding for the first batch of wind power equipment for the 2026 wind power projects of China Coal Corporation was held. CSSC Haizhuang was the first winning bidder, with a bid price of 820,351,800 yuan. The project involves the procurement of wind power equipment (including towers and anchor bolts) for the 336.6MW thermal power transformation project and 90MW plant power supply new energy project of China Coal Northwest Company.


3. 中节能第二个海上风电项目,中标结果定了!

3. The second offshore wind power project of Sinovel has been awarded! The result has been determined.


5月26日,中节能风力发电股份有限公司某海域海上风电项目前期工作总包服务、某海域资源环境调查评估与风电开发条件研究服务邀请招标中标结果公布。

On May 26th, the results of the invitation bidding for the overall project management services for the offshore wind power project in a certain sea area, as well as the services for resource and environmental investigation and assessment, and research on wind power development conditions in the same sea area, were announced.


某海域海上风电项目前期工作总包服务:

3. The second offshore wind power project of Sinovel has been awarded! The result has been determined.


公告显示,中标单位:中国电建集团华东勘测设计研究院有限公司(联合体牵头人)、中国能源建设集团江苏省电力设计院有限公司(联合体成员),中标金额(含税):99800000.00元。

The announcement states that the winning bidder is: China Electric Power Construction Group East China Survey and Design Institute Co., Ltd. (the lead entity of the consortium) and China Energy Construction Group Jiangsu Electric Power Design Institute Co., Ltd. (a member of the consortium), and the winning bid amount (including tax) is: 99,800,000.00 yuan.


某海域资源环境调查评估与风电开发条件研究服务:

Service for Investigation and Assessment of Marine Resources and Environment and Research on Wind Power Development Conditions:


公告显示,中标单位:中国电建集团中南勘测设计研究院有限公司(联合体牵头人)、自然资源部东海海域海岛中心(自然资源部东海信息中心)(联合体成员),中标金额(含税):24580000.00元。

The announcement states that the winning bidder is: China Electric Power Construction Group Central South Survey and Design Institute Co., Ltd. (the lead entity of the consortium), and the Natural Resources Department East Sea Islands Center (the Natural Resources Department East Sea Information Center) (a member of the consortium). The winning bid amount (including tax): 24,580,000.00 yuan.


4. 总投资14.21亿元!陕西3个风电项目签约

4. Total investment of 1.421 billion yuan! Three wind power projects in Shaanxi have been signed.


5月21日,横山区招商引资推介会暨西安市横山商会二届三次会员代表大会举行,集中签约多个重点项目,总签约额超过45亿元。

On May 21st, the investment promotion promotion meeting of Hengshan District and the second-third session of the members' congress of Xi'an Hengshan Chamber of Commerce were held. A number of key projects were signed in a concentrated manner, with the total signing amount exceeding 4.5 billion yuan.


其中新能源项目包括西安隆基清洁能源有限公司投资10亿元的30万千瓦光伏发电项目、陕西中济新能源有限公司投资5.51亿元的10万千瓦风电项目、阳光新能源开发股份有限公司投资6亿元的10万千瓦风电项目、陕西龙源新能源有限公司投资2.7亿元的二期5万千瓦风电项目、榆林科创优能科技有限公司投资3亿元的5万千瓦零碳分布式智慧能源供应项目。  

Among the new energy projects are the 300,000-kilowatt photovoltaic power generation project with an investment of 1 billion yuan by Xi'an Longji Clean Energy Co., Ltd., the 100,000-kilowatt wind power project with an investment of 551 million yuan by Shaanxi Zhongji New Energy Co., Ltd., the 100,000-kilowatt wind power project with an investment of 600 million yuan by Sunlight New Energy Development Co., Ltd., the second phase 50,000-kilowatt wind power project with an investment of 270 million yuan by Shaanxi Longyuan New Energy Co., Ltd., and the 50,000-kilowatt zero-carbon distributed smart energy supply project with an investment of 300 million yuan


5. 广西90MW风电项目开工建设!

5. The 90MW wind power project in Guangxi has started construction!


5月20日,中国电建重庆工程公司广西象州古才风电场EPC总承包项目开工建设,项目装机容量90兆瓦,建设12台单机容量6.25兆瓦和3台单机容量5.0兆瓦风力发电机组。  

On May 20th, the EPC general contracting project of the Guacai Wind Farm in Xiangzhou, Guangxi, of China Electric Power Construction Chongqing Engineering Company was officially launched. The project has an installed capacity of 90 megawatts, and will construct 12 wind turbines with a capacity of 6.25 megawatts each and 3 wind turbines with a capacity of 5.0 megawatts each.


6. 中核集团海南600MW海上风电项目启动!

6. China Nuclear Group's 600MW Offshore Wind Power Project in Hainan Has Been Initiated!


5月22日,中核集团电子采购平台发布《中核海南昌江60千瓦海上风电项目前期工作咨询服务招标公告》。 招标范围:本次招标范围为中核海南昌江60万千瓦海上风电项目前期工作咨询总承包,含前期技术咨询服务、前期行政许可审批办理咨询及相关内容。

On May 22nd, the electronic procurement platform of China National Nuclear Corporation released the "Bidding Announcement for Preparatory Work Consultation Services for the 60-Kilowatt Offshore Wind Power Project in Changle, Hainan". The scope of the bidding: The scope of this bidding is the overall consulting services for the preparatory work of the 600,000-kilowatt offshore wind power project in Changle, Hainan, including pre-technical consulting services, pre-administrative permit approval processing consultation, and related contents.


7. 东方电气埃塞俄比亚最大风电项目第二阶段首台风机成功吊装!

7. The first wind turbine of the second phase of Dongfang Electric's largest wind power project in Ethiopia was successfully lifted into place!


近日,由东方电气承建的埃塞俄比亚最大风电项目阿伊萨风电项目第二阶段首台风机顺利完成吊装。该项目共安装48台东方电气2.5兆瓦风力发电机组,总装机容量120兆瓦,一期工程已于今年1月投产。  

Recently, the second phase of the Aisa Wind Power Project, the largest wind power project in Ethiopia, successfully completed the hoisting of its first wind turbine. This project installs 48 wind turbines from Dongfang Electric, each with a capacity of 2.5 megawatts. The total installed capacity is 120 megawatts. The first phase of the project was put into operation in January this year.


8. 大唐300MW风电项目获核准

8. The 300MW wind power project of Datang has been approved.


2026年5月22日,大唐集团河南公司太康300MW风电项目获核准,项目建设场址位于周口市太康县,规划建设规模为300MW。  

On May 22, 2026, the 300MW wind power project of the Henan Branch of Datang Group was approved. The project construction site is located in Taikang County, Zhoukou City. The planned construction scale is 300MW.


9. 三峡能源500MW海上风电项目公示!

9. Public announcement of the 500MW offshore wind power project of Three Gorges Energy!


近日,大连市海洋发展局发布《大连市海上风电场址DL6项目海域使用论证报告书公示》,三峡(辽宁)能源投资有限公司拟在辽宁省大连市庄河南部海域建设500MW海上风电项目,规划安装32台13MW和6台14MW风电机组,并建设海上升压站及陆上集控中心,项目用海期限27年,施工期约18个月。  

Recently, the Dalian Municipal Bureau of Marine Development released the "Public Notice of the Marine Use Argument Report for the DL6 Project of Dalian Offshore Wind Farm". China Three Gorges (Liaoning) Energy Investment Co., Ltd. plans to build a 500MW offshore wind power project in the southern part of Zhuanghe Sea, Liaoning Province. It is planned to install 32 13MW and 6 14MW wind turbines, and build an offshore substation and an onshore control center. The project's marine use period is 27 years, and the construction period is approximately 18 months.


10.  华能1.32GW风电项目开标,这两家整机商预中标

10. The bidding for the 1.32GW wind power project of Huaneng has been concluded. These two manufacturers of complete wind turbine systems have been pre-selected as the winners.


5月27日,华能新疆公司楼兰风电等14个风电项目共计2456.4MW风力发电机组及其附属设备集中采购预招标(标段四、五)中标候选人公示,规模共计1321.4MW。

On May 27th, the winning bidders for the centralized procurement pre-bidding (segments 4 and 5) of 14 wind power projects including Longlan Wind Power of Huaneng Xinjiang Company and other projects, involving a total of 2456.4MW of wind power generating units and their affiliated equipment, were announced. The total scale amounts to 1321.4MW.


标段四(741.4MW):东方风电预中标,投标总价125211.5万元;

Segment 4 (741.4MW): Dongfang Wind Power has been preliminarily awarded the contract, with a total bid price of 125,211.5 million yuan.


标段五(580MW):远景能源预中标,投标总价108611.25万元。

Segment 5 (580MW): Yundian Energy has been preliminarily selected as the winner. The total bid price is 108,611,250,000 yuan.


据悉,3月5日,华能新疆公司楼兰风电等14个风电项目共计2456.4MW风力发电机组及其附属设备集中采购预招标公告发布。集采分为6个标段、14个风电项目,项目规模合计2456.4MW,本次招标不含塔筒。其中一、二、三标段已于4月24日开标。

It is reported that on March 5th, the pre-bidding announcement for the centralized procurement of a total of 2456.4MW wind turbine generators and their ancillary equipment for 14 wind power projects of Huaneng Xinjiang Company, including Loulan Wind Power Project, was released. The centralized procurement was divided into 6 sections and 14 wind power projects, with a total project scale of 2456.4MW. This bidding does not include tower frames. The first, second and third sections were opened for bidding on April 24th.


11. 京能180MW风电项目获核准批复!

11. Jingeng 180MW Wind Power Project has received approval and authorization!


5月26日,京能四子王旗10万千瓦风电项目获核准批复,总投资约3.79亿元,年均可输送清洁电能超2.5亿千瓦时。5月27日,京能青龙二期风电项目也获核准,装机容量8万千瓦,年发电量约1.7亿千瓦时。  

On May 26th, the 100,000-kilowatt wind power project of Jingneng Siziwangqi was approved. The total investment is approximately 379 million yuan, and it can supply over 250 million kilowatt-hours of clean electricity annually. On May 27th, the Jingneng Qinglong Phase II wind power project was also approved. With an installed capacity of 80,000 kilowatts, it will generate approximately 170 million kilowatt-hours of electricity annually.


12. 1911元/kW!三一重能预中标国能100MW风电项目

12. 1911 yuan/kW! Sany Renewable Energy has been pre-selected to win the bid for the 100MW wind power project of GuoNeng.


5月28日,国家能源集团2026年第1批风力发电机组集中采购公开招标项目中标候选人公示,本次开标为标包二:内蒙古公司元宝山电厂火电灵活性改造消纳新能源100MW风电项目(100MW)集中采购项目,三一重能预中标,投标报价19110万元,含塔筒单价1911元/kW。项目规划容量100MW,拟安装13台7.X MW风力发电机组。

On May 28th, the list of winning bidders for the first batch of wind turbine equipment centralized procurement project of the National Energy Group in 2026 was announced. This tendering session was for package two: the centralized procurement project for the thermal power flexibility transformation and new energy accommodation of the Baonanshan Power Plant of Inner Mongolia Company (100MW), which is a wind power project (100MW). Sany Heavy Energy was the pre-winner, with a bid price of 191.1 million yuan, including a tower cylinder unit price of 1,911 yuan/kW. The planned capacity of the project is 100MW, and 13 units of 7.X MW wind turbines are to be installed.


13. 金风科技预中标!中广核240MW风电项目

13. Jinfeng Technology has been preliminarily awarded the contract! CGN's 240MW wind power project


5月29日,中广核新能源云南文山州那来、新华240MW陆上风电项目风力发电机组设备采购中标候选人公示,金风科技预中标,投标报价504,711,000.00元。

On May 29th, the list of winning bidders for the wind turbine equipment procurement of the Nala Wind Farm project in Wenshan Prefecture, Yunnan Province, and the 240MW onshore wind power project of Xinhua was announced. Goldwind Technology was pre-selected as the winner, with a bid price of 504,711,000.00 yuan.