摘要:为确保吊装工作顺利进行,该公司全过程参与大板梁驻场监督、大件运输、道路修整、专项吊装方案研讨等工作。多次组织专业会议,讨论确定吊装现场技术要求、施工工艺、作业流程、安全措施、应急救援等内容。吊装前认真梳理并逐一确认“人、机、法、料、环”细节,吊装..
为确保吊装工作顺利进行,该公司全过程参与大板梁驻场监督、大件运输、道路修整、专项吊装方案研讨等工作。多次组织专业会议,讨论确定吊装现场技术要求、施工工艺、作业流程、安全措施、应急救援等内容。吊装前认真梳理并逐一确认“人、机、法、料、环”细节,吊装过程中,建设单位、监理单位、施工单位全程旁站监护,指挥人员与操作人员协调一致、配合默契,确保了大板梁高标准同步吊装就位,为后续受热面吊装及施工奠定了坚实基础。
In order to ensure the smooth progress of lifting work, the company participated in the whole process of large slab beam on-site supervision, large transportation, road repair, special lifting program discussion and other work. Organize professional meetings for many times to discuss and determine the technical requirements, construction technology, operation process, safety measures, emergency rescue and other contents of the hoisting site. Before hoisting, carefully comb and confirm the details of "people, machines, methods, materials and rings" one by one. During the hoisting process, the construction unit, supervision unit and construction unit will stand by the side to monitor the whole process, and the command personnel and the operator will coordinate and cooperate with each other, ensuring that the high standard of the large slab beam is hoisted into place simultaneously, laying a solid foundation for the subsequent hoisting and construction of the heating surface. Beihai Power plant phase II expansion project in strict accordance with the group company's "construction with efficient environmental protection, intelligent production, intelligent management and other characteristics of The Times, with clean, integrated, refined, intelligent, international and other group characteristics, with regional deep integration, the project's own infrastructure characteristics" project construction policy, created a "simultaneous construction" management model of infrastructure projects. |